Bad weather 2019 and governance vacuum in 2020 delayed the project and added extra cost to the budget. (Mirror file photo)

New cost of Sayward dam project almost $1.2 million

Costs have increased by another $208,513 after previous cost increases in 2019 and 2020

  • Dec. 8, 2020 12:00 a.m.

Sayward’s Newcastle Creek Dam is back on track for completion after sustaining delays in 2019 and 2020, according to newly-elected mayor Mark Baker.

But the delays have caused an increased cost to the project of $208,513, pulling the new total cost up to $1,194,726.

According to the town’s latest project cost summary document, an additional $60,000 has been added towards project management, engineering and environmental consultation, $98,513 in construction costs and $50,000 has been added to the project’s contingency fund.

The rehabilitation of the dam was previously set for completion in 2020 at an cost of $1,162,896 after bad weather in 2019 set back the project and had already increased the project cost by $176,783.

Further delays in 2020 – as Sayward faced a governance vacuum after the resignation of council members – added another $31,730 to the cost of the dam.

All financial decisions pertaining to the dam were put on hold until December when a new mayor and two council members were elected.

READ MORE: Sayward elects new mayor and two council members

Sayward’s council is looking to adjust the additional costs by diverting $158,513 from from the general surplus funds and $50,000 from the water surplus funds.