The City has completed some of its milling and paving work this week.
Completed milling and paving works include the areas of Second Avenue, from Oliver Street to Mackenzie Avenue, and Third Avenue, from Barnard Street to Mackenzie Avenue.
Milling of Oliver Street, between Eighth and Mackenzie avenues has also been completed, with paving expected to have begun last night, weather permitting.
Milling is expected to begin on 11th Avenue North, from Smedley Street to Highway 97, and Toop Road, from Centennial Drive to Highway 97.
The City says flagging crews will assist in directing traffic, and motorist co-operation is appreciated.
No street parking will be allowed on these stretches of street when “no parking” signs are displayed.