After a year’s delay, the sidewalk on Shuswap Street will be replaced.
The stretch between 2nd Street SE and Fifth Street SE was put on hold in the city’s 2020 budget in order to save funds during the pandemic.
Staff noted in a recent report that the west of the street was upgraded with the construction of the Downtown Education Centre and the improvements to the frontage of the Jackson property.
“The sidewalk on the east side is very old and in very poor condition and in need of replacement. The existing cracks and grade separations create a significant trip/fall hazard,” said the report.
Along with the new sidewalk there will also be a ‘bump out,’ the curb that extends into the street at a pedestrian crossing in hopes of improving pedestrian safety.
The work was awarded to Little Projects Ltd. at a low bid of $211,000. The company is proposing to complete the project in September or October of this year.
Read more: Salmon Arm city sidewalk buckles in extreme heat
Read more: Salmon Arm tackles cracked sidewalks, potholes, despite lack of 1-800 number
martha.wickett@saobserver.netLike us on Facebook and follow us on Twitter
and subscribe to our daily newsletter.